Certified Standards The Anti Noise Quality Guarantee

Every installation completed by Lunar Solar meets rigid UK electrical, structural, and renewable energy mandates. We protect your home, roof, and investment with fully verified accreditations.

MCS Accredited

Why it matters

Mandatory for claiming Smart Export Guarantee (SEG) cashbacks from energy suppliers and guaranteeing solar panel and inverter efficiency standards.

Why it matters

Proves our electricians hold advanced Level 3 awards in solar PV and battery storage allowing us to self-certify Part P Building Regulations work.

FULL COMPETENT PERSON SCHEME (CPS)

Why it matters

Guarantees strict consumer protection deposit protection insurance and compliance with the UK Code of Conduct.

Government Endorsed Standard

Why it matters

F-gas air conditioning systems must be installed by qualified engineers from certified businesses to ensure safe handling, prevent leaks, and protect the environment.

F-Gas Certified

What Our Accreditations Guarantee for Your Property

Frame 2147230561

SEG Export Payment Registration Support

Without an MCS certificate, UK energy suppliers legally cannot register your system for Smart Export Guarantee payments. We lodge your installation on the central MCS database within 10 days of commissioning.

Frame 2147230562

Part P Building Control Sign-Off

Electrical safety compliance is automatically notified to your Local Authority Building Control through our NAPIT membership. You will receive a formal Building Regulations Compliance Certificate upon completion.

Insurance-Backed Guarantees (IBG)

Your deposit and workmanship guarantees are protected independently, ensuring total peace of mind for decades to come.

Wind Uplift & Structural Load Calculations

All mounting equipment is installed in full compliance with MCS 012 structural standards, engineered specifically for British wind zones and varied roof tile types.

e21ccc9b6737a90015438c42355cdfe751a87957
b67eea3a06f6777e0ec152a421c9b06c32c31e25
71b99020b2655517debda95ff04e6395816c3da9 (1)

Friction-Free DNO Paperwork Handling

We handle 100% of the Distribution Network Operator (DNO) paperwork, grid notifications, and connection approvals on your behalf—zero bureaucracy for you.

GRID CONNECTION SUPPORT

Fit and Inform

For standard residential solar arrays (up to 16A per phase), we install your system and notify your regional DNO (e.g., National Grid, UK Power Networks, SSE) within 28 days of commissioning.

G98 Grid Notification (Systems ≤ 3.68kW per phase)

Prior Approval

For larger solar arrays or high-output battery systems, we submit technical single-line diagrams (SLDs), inverter protection settings, and export limitation calculations prior to installation to secure formal DNO approval.

G99 Grid Application (Systems > 3.68kW or Large Batteries)

How We Process Your DNO Approval in 3 Steps

DNO APPROVAL PROCESS

Pre-InstallationTechnical Assessment & MPAN Verification

We inspect your electricity meter's main fuse rating (60A, 80A, or 100A), and verify your Meter Point Administration Number (MPAN).

Application Submission & Technical Engineering

We draft the full G98/G99 application paperwork including technical inverter schematics and factory test certificates and submit it directly to your DNO.

Final Acceptance Letter & SEG Handover

Once approved, we deliver your official DNO Acceptance Letter alongside your MCS Certificate, unlocking top-tier export tariffs immediately.

FREE ASSESSMENT

Turn Your Roof into a Private Power Plant Today

Find out how many panels fit your roof and receive a full financial breakdown within 24 hours.

COMMON QUESTIONS

Frequently Asked Questions About Accreditations & DNO Approval

A DNO Acceptance Letter is an official document from your regional electricity network operator confirming that your solar/battery installation is registered and approved to connect to the National Grid.

No. Lunar Solar handles all communications, application submissions, and technical paperwork with your DNO from start to finish.

In rare cases where local grid infrastructure is congested, we install smart G99 export limitation devices that cap grid export while allowing 100% of generated solar power to be used inside your home or stored in your battery.

NAPIT membership certifies that our installation team meets high electrical standards, allowing us to legally certify electrical work under Part P of UK Building Regulations and automatically notify your local council.

2ddf0ce63e969bc3827cc4bbdcaf8598c339d352

Have Questions About Grid Approvals or Standards?

Speak directly with our technical compliance team, or request a zero-pressure roof survey.